X can do a piece of work in 20 days and Y can do it in 12 days. Y worked at it for 9 days. In how many days can X alone finish the remaining work?
Solve this multiple-choice question and check the correct answer with its explanation below.
Answer options
Correct answer and explanation
Correct answer: 5
Explanation: ā Correct Answer: A) 5 š Explanation: Y can finish the work in 12 days, so in 9 days, Y completes 9/12 or 3/4 of the work. This leaves 1/4 of the total work remaining for X. Since X can do the whole work in 20 days, he will take 1/4 of that time for the remainder. Calculating 20 * (1/4) shows that X needs 5 more days to finish alone.